working principle
Secondary Crusher Fineness 20-120 mesh
This machine is composed of three parts: frame, crushing body and feeding hopper. The main working principle is: a movable toothed disc is installed on the main shaft. Install three circles of movable knives on the movable toothed disc. In addition, a fixed tooth plate is installed in the crushing body door. There are two rings of fixed ring gears with sawtooth on the fixed tooth disc. When the main shaft is running at high speed, because the movable teeth on the movable tooth disc and the steel ring rings on the fixed gear ring are arranged alternately, the movable ring gears rotate relatively, so that the material Under the comprehensive action of shearing, impact, friction between fixed teeth and movable teeth, and impact and collision between materials, the materials are crushed to achieve the purpose of crushing. This machine is simple in structure, sturdy and durable, stable in operation, low in noise, obvious in crushing effect and convenient in maintenance. It is an ideal special equipment for crushing materials.
The machine has been installed and debugged before leaving the factory. When the goods arrive at your company, just connect three wires and start to use, which is convenient and quick.
1. After the machine is in place, it must be installed on a horizontal ground plane. If necessary, the feet can be fixed with bolts to prevent movement.
2. After adjusting the level, first check the lubricating grease on the bearing part. Generally speaking, the machine has been injected with an appropriate amount of lubricating grease before leaving the factory.
3. Check whether the fasteners of each part of the machine are tightened. Check whether the door of the machine cavity is closed and sealed well, and then move the belt by hand to check whether there is any jamming and abnormal sound.
4. Before turning on the machine, check whether there is any foreign matter such as metal in the machine cavity, otherwise it will damage the machine cavity, the gear plate or cause accidents.
5. Connect the power supply and check the rotation direction of the main shaft. It must be in accordance with the arrow direction of the machine, otherwise the machine cavity and the toothed disc will be damaged.
6. The electrical part must have a reliable grounding protection to prevent accidents.
7. When starting up the machine, run it dry for ten minutes first, and then start trial crushing after it is normal. open first
The gate of the hopper allows the material to flow into the crushing cavity. When feeding, it must be distributed evenly. After the crushing is completed, the cavity must be cleaned to prevent cross-contamination.
Technical Parameters
| 型号 | WF-15B | WF-20B | WF-30B | WF-40B | WF-60B | WF-80B |
| 生产能力(KG) | 10-50 | 20-80 | 30-200 | 50-300 | 150-500 | 250-800 |
| 进料粒度(mm) | ≤6 | ≤6 | ≤6 | ≤6 | ≤6 | ≤6 |
| 出料粒度(目) | 60-120 | 60-120 | 60-120 | 60-120 | 60-120 | 60-120 |
| 功率(kw) | 2.2 | 4 | 5.5 | 11 | 18.5 | 37 |
| 主轴转速(转) | 3200 | 3000 | 2900 | 2900 | 2900 | 2900 |
| 外形尺寸(MM) | 350×380×880 | 550×420×1088 | 770×750×1500 | 970×850×1708 | 1200×950×2000 | 1500×1200×2200 |
| 重量(KG) | 150 | 200 | 300 | 400 | 500 | 700 |